A new conveyor belt is one of the few purchases where the installation crew can quietly decide the component's service life. A spindle bent while the idler was stacked, a splice cured short on pressure, a splice cured short on pressure: none of it stops the commissioning schedule that day. All of it surfaces as downtime later, when the warranty conversation has become a disagreement about records.
Procurement owns part of this outcome. The RFQ either asks for installation tolerances, splice cure records and function-test sheets, or it does not. This article turns the pre-start inspection into a list a buyer can put in a contract, with the checks in the order a crew should run them and the paperwork that makes each check enforceable. It applies to any belt conveyor handling run-of-mine or processed material.
Industry context. The timing matters because new conveyors are being commissioned at a steady clip. At Brightstar Resources' Laverton gold project in Western Australia, primary crushing concrete was poured in October 2026 and EPC progress reached 50 percent as of 10 November 2026, according to Australian Mining, with the ROM pad connection underway. Coal handling systems are under similar pressure elsewhere: Indian coal-fired generation rose 25.7 percent year on year in October, the fastest pace in three years, per Economic Times data carried on 8 November 2026, pushing fuel-handling belts toward sustained high utilization. More first starts, and less margin for sloppy ones.
A commissioning check is any inspection performed between mechanical completion and first loaded run on a conveyor belt system that has a recorded result and a named person responsible for it. Anything without a record is an opinion, and opinions do not support warranty claims.
Three groups cover a belt conveyor:
| Group | What it covers | Typical records |
|---|---|---|
| Belt material | Splice, cover, edges, storage condition | Cure chart, splice photos, defect list |
| Structure | Idlers, pulleys, stringers, take-up, loading zone | Squareness measurements, rotation log, torque marks |
| Protection | Cleaners, skirting, safety devices, sensors | Function-test sheet, settings log |
A buyer reading a contractor's method statement should see all three groups with dates and signatures. If the statement only says "inspect conveyor," that is a quotation, not a plan.
![]()
A plant conveyor carrying crushed stone. The wear pattern of its first month was decided during installation.
A belt runs on friction and geometry. The drive pulley converts torque through the lagging and the wrap angle, which only works when tension meets the grip calculation. The conveyor idlers and rollers hold the belt's shape, which only works when each frame is square and level to the centerline. The loading zone feeds material onto the belt center, which only works when the chute and the skirting are set with the right gaps.
Disturb any of these and the belt steers itself somewhere it should not go. Off-square pulleys cause persistent mistracking that no training idler fixes, because the correction fights the geometry on every revolution. Once the geometry is honest, an automatic belt tracking unit holds center cheaply for years. Skirting pressed hard into a new cover cuts a groove that deepens every day. A belt trained empty then loaded without re-checking drifts again, because the load pushes the belt down into the trough and shifts the balance.
The startup sequence follows the same logic: settle the belt empty, establish geometry, then add load gradually and re-verify. Jog two or three times, run at low speed, watch one full belt revolution on foot, track tail to head one adjustment at a time, then feed at 25 percent of design tonnage and step up while reading idler temperatures with an infrared gun.
The payback comes in four forms, none of them dramatic on their own:
None of this adds cost beyond labor. The checks run while the belt is stopped and access is easy, which is the cheapest condition a conveyor will ever offer.
The same list applies everywhere, with three areas where crews should spend extra time:
Acceptance is also the moment to confirm you received the material you paid for:
| Component | What to verify at handover | Common gap |
|---|---|---|
| Belt cover grade | Cover compound matches the RFQ spec, not "standard" | Supplier substituted a lower grade at dispatch |
| Splice | Cure chart with time, pressure, temperature | No cure record on site |
| Idler bearings | Seal type and bearing brand as quoted | Generic unbranded bearings fitted |
| Impact bed bars | Bar compound and rated lump size | Bars swapped for softer stock |
| Skirting | Polyurethane hardness as specified | Hardness unmeasured on delivery |
Every row is a one-page check with a phone camera and a hardness tester. Every row is also a dispute you cannot win later without the record.
| Item | Crew can verify | Needs contractor or supplier input |
|---|---|---|
| Idler rotation by hand | Yes | - |
| Pulley squareness | With a tape and string line | Laser alignment for long belts |
| Splice quality | Visual and coin tap | X-ray on steel cord, cure chart |
| Tension setting | Sag check | Take-up calculation and torque records |
| Safety devices | Function test | Certification where required |
Split the list in the contract. Crew checks fail quietly when the crew was never told they own them.
| Industry | Dominant early-life failure | Checklist emphasis |
|---|---|---|
| Gold, crushing circuits | Impact damage at ROM feed | Impact bed spec, lump height |
| Coal handling | Splice and edge wear, high utilization | Tension record, tracking under load |
| Iron ore | Abrasive carryback and skirt wear | Skirting contact, cleaner setup |
| Aggregate quarries | Misalignment after relocation | Full geometry pass every move |
| Mineral sands | Fine carryback to return idlers | Cleaner pressure, plough clearance |
The cheapest time to enforce the checklist is before the purchase order. Four clauses do most of the work:
A supplier who resists clause one is telling you something useful. Most will not.
Run the acceptance in this order and initial each line:
| Step | Check | Pass condition | Who signs |
|---|---|---|---|
| 1 | Splice and belt condition | Cure record complete, no defects past dress limit | QC + contractor |
| 2 | Idlers | Every unit rotated, no grind or dent, frames square | Contractor |
| 3 | Pulleys | Lagging intact, square within tolerance, bearings free | Contractor |
| 4 | Tension | Take-up at calculated position, sag within spec | Contractor + owner |
| 5 | Loading zone | Chute centered, skirting light contact, impact hardware set | Contractor |
| 6 | Cleaners | Blade angle set, backed off for empty run | Contractor |
| 7 | Safety devices | Every pull cord, e-stop and switch function-tested | Electrical + owner |
| 8 | Empty run | Full revolution walked, tracking corrected tail to head | Operations |
| 9 | Stepped loading | 25% to 100% tonnage, no drift, no spillage, no hot idlers | Operations |
| 10 | File closed | All records archived, spares in stores | Owner |
For component supply, a Mining Secondary Belt Cleaner and spare blades should ship with the original order, and the supplier should state the blade backing-off procedure in writing so it can be checked at step 6.
| Problem in month one | Likely handover gap | Corrective owner |
|---|---|---|
| Edge feathering | Tracking never finished under load | Contractor returns |
| Splice break | Cure record missing or short | Supplier claim, file decides |
| Hot idler bearings | Rotation check skipped | Installation crew |
| Cover grooving | Cleaner set hard on day one | Fitting procedure gap |
| Spillage at skirts | Sealing gap wrong, chute off center | Contractor adjustment |
![]()
The first loaded run at low tonnage is the last cheap chance to catch handover gaps before they become month-one failures.
The commissioning file is a maintenance schedule in draft form. Take-up position becomes the reference for every tension check. The idler temperature log becomes the baseline the infrared gun compares against. Squareness measurements tell the next crew what "correct" looked like. Splice photos date the splice. File the paper where the maintenance planner can reach it, and the checklist keeps paying after the project team leaves site.
Customer Type: A coal handling terminal serving coastal power stations.
Ore Type: Thermal coal, high fines, damp after washing.
Operating Conditions: 1,800 mm belt, 2,500 tph design, high-drop transfer from ship loader feed.
Problem: On a previous conveyor, the terminal ran first ore a day early and skipped the idler rotation check. Four seized spindles inside two months followed, and the installer dispute went nowhere because no records existed.
Solution: For the next conveyor, the owner made the commissioning file a payment milestone. Splice cure records, idler rotation log, squareness measurements, tension calculation and safety function tests were all signed before first ore, and the first loaded run stepped from 25 to 100 percent tonnage over two shifts with temperature readings every hour.
Result: No unplanned stoppages in the first quarter, and one idler replaced during commissioning at the contractor's cost after the rotation check found a dented shell. The checklist was cheaper than the last conveyor's first quarter.
Q1: How long should a new conveyor belt run empty before loading?
Long enough for one full belt revolution at operating speed with tracking corrections done, usually under an hour. Then load in steps of 25 to 50 percent of design tonnage rather than jumping to full rate.
Q2: What tension should a new belt be set to?
To the manufacturer's take-up calculation, built from the drive grip requirement, sag limits and starting condition. Set the minimum that prevents slip at starting torque, confirm sag between idlers, and record the take-up position. Over-tensioning loads the splice and bearings for no benefit.
Q3: Who pays if an idler arrives damaged and gets installed anyway?
Whoever the contract says owns transit and installation damage. An inspection before erection, with photos, puts dented shells on the supplier's account while the evidence is still in the crate.
Q4: Do I need to re-track the belt after it is loaded?
Usually slightly. The load pushes the belt into the trough and shifts the balance, so a belt trained empty may drift a few millimeters loaded. Track empty first, then correct in small steps as tonnage rises.
Q5: Which pre-start check is most often skipped?
Hand-rotation of every idler, because it is slow. The cost appears weeks later as a hot bearing that seizes or drags the belt. The half-day this check takes is the cheapest insurance on the list.
Q6: What records does a belt warranty claim actually need?
Cure chart, splice photos, tension and take-up records, squareness measurements, and evidence the belt ran within tolerance before failure. The commissioning file is the claim file.
Q7: Should belt cleaners touch the belt during the empty run?
No. Secondary belt cleaner blades follow the same rule. Fit them at the correct angle, back the blades off, then bring them to working pressure during the stepped loading runs. A cleaner set hard on day one grooves the cover for the belt's life.
Q8: How do I verify skirting is set correctly before first ore?
The sealing strip touches the belt with light contact along its full length, with no hard press and no visible gap under load. Check it again after the first loaded hour, when the belt settles into the trough.