Exciting force in this context refers to two related but different quantities: the dynamic force associated with producing a target motion in the vibrating mass, and the centrifugal force generated by the rotating unbalanced masses inside the exciter.
Effective vibrating mass (M_v) is the mass that participates in operating vibration — screen box, decks, screen media, cross members, exciter assemblies and a defined portion of the material carried on the deck.
Static moment (M_s) is the sum of each eccentric mass multiplied by its distance from the rotation axis, expressed in kg·m or kg·cm. It is the geometric property that, combined with speed, determines the generated force.
Target acceleration (K) is the required peak acceleration expressed as a multiple of gravitational acceleration.
The calculation connects two physical relationships and accounts for the machine's dynamic response.
The force required. Newton's second law gives F = m × a. For a vibrating screen, the mass is the effective vibrating mass, and the acceleration is K times gravity. The result is the inertial force associated with accelerating the screen body through its motion.
The force generated. A rotating unbalanced mass generates centrifugal force proportional to its mass, its radius from the rotation axis, and the square of angular velocity. Multiple masses acting in the same direction and correctly phased add their contributions.
Why they are not the same calculation. In a spring-supported, damped vibrating system, the applied force and the resulting displacement are related through the system's dynamic response, not through a simple multiplication. Near resonance, the relationship between force and displacement changes significantly. Spring restoring force, damping, phase relationships, screen-body rotation and coupling between translational and rotational motion all affect how the generated force produces the required motion.
Where the sizing check fits. The calculation gives a preliminary static moment requirement. That static moment must then be matched against the exciter manufacturer's available working-moment range, bearing load capacity, shaft strength, permissible speed and mounting interface. A preliminary match that satisfies static moment does not automatically satisfy bearing life or structural limits.
Correct exciter sizing when effective mass and target acceleration are established from validated data.
Avoided oversizing when full throughput is not mistakenly included as vibrating mass.
Avoided undersizing when amplitude and stroke are correctly distinguished.
Cross-check confidence when amplitude measurement confirms the acceleration target.
Better supplier conversations when operating data and mass basis are provided.
Reduced risk of structural overload when force increase is evaluated against structural limits before adjustment.
Large mining screens in iron ore, copper ore, gold ore and base metal circuits.
Aggregate processing screens operating continuously under abrasive duty.
Coal preparation where wet screening and variable feed apply.
Multi-exciter linear screens where force division and synchronization are critical.
Replacement exciter selection where existing operating data provides the basis.
Process change evaluation where feed rate, density or stroke has changed.
These duties sit between size reduction in CRUSHING and downstream CLASSIFICATION or DEWATERING. Sizing affects the entire circuit, not only the deck.
| Property | Inertial Force Calculation | Centrifugal Force Calculation | Cross-Check from Amplitude |
|---|---|---|---|
| Input | Effective mass, target acceleration | Static moment, speed | Measured amplitude, speed |
| Output | Required dynamic force | Force generated by weights | Acceleration as G-force |
| Purpose | Establish the force the screen needs | Establish the force the exciter provides | Verify consistency |
| Common error | Including full throughput as mass | Using stroke as amplitude | Unreliable measurement point |
| When to use | Preliminary sizing | Exciter selection | Post-installation verification |
| Scenario | Dominant Calculation Issue | Recommended Approach |
|---|---|---|
| New exciter selection | Mass basis not established | Obtain effective mass from design data, not shipping weight |
| Replacement of an existing exciter | Existing speed and moment known | Use nameplate and measured amplitude for verification |
| Amplitude appears low | Stroke vs amplitude confusion | Confirm measurement convention before calculating |
| Process change evaluation | Vibrating mass or duty has changed | Recalculate with new mass and acceleration target |
| Dual exciter balance | Force division assumption | Verify synchronization and phase from the drawing |
| Speed adjustment consideration | Force scales with ω² | Evaluate against structural and bearing limits first |
| Industry | Typical Screen | Calculation Priority | Common Error |
|---|---|---|---|
| Iron ore | Large heavy-duty screens | Effective mass and target acceleration | Including oversize feed as vibrating mass |
| Copper | SAG discharge screens | Exciter arrangement and speed | Assuming equal force division between exciters |
| Gold | Multi-deck screens | Per-deck mass contribution | Using overall mass for a single deck calculation |
| Coal | Wet screening screens | Material mass contribution | Treating wet material as dry mass |
| Aggregates | Two-deck and three-deck screens | Amplitude and stroke convention | Using stroke as amplitude |
| Sand and gravel | Compact screens | Speed conversion from rpm | Force comparison without ω² conversion |
| Industrial minerals | Fine screens | Acceleration target from design | Using generic K value |
| Base metals | Grinding circuit screens | Bearing and structural verification | Sizing on force alone |
| Phosphate | Wet screens | Effective mass with moisture | Dry mass assumption |
| Tailings | Dewatering screens | Amplitude from commissioning data | Confusing peak-to-peak with single amplitude |
1. Establish the mass basis. Effective vibrating mass includes screen box, decks, media, cross members, exciter assemblies and the defined material portion. State clearly whether the figure is empty, loaded or design case.
2. Obtain the target acceleration. From screen design or a validated calculation for the specific duty. Do not use a generic K value across applications.
3. Calculate the preliminary required force. F_r = M_v × K × g. Convert newtons to kN for practical sizing.
4. Convert operating speed to angular velocity. ω = 2πn / 60. Force scales with ω², so speed conversion accuracy matters.
5. Calculate required static moment. M_s = F_r / ω². Convert between kg·m and kg·cm carefully — a factor of 100 difference.
6. Account for exciter arrangement. Single versus dual, circular versus linear, phase relationship. Divide force between exciters only after confirming the configuration shares it equally.